We get asked all the time, “How long is my project going to take?”. And well, the response is almost never what people expect. We’re sorry to be the bearer of bad news, but the popular home-remodeling TV shows have given an unrealistic expectation of how long a kitchen remodel should take! In reality (real reality, not reality television 🙂 ), a real-life kitchen remodel, given the time and expertise, cannot be done in a weekend, two weeks, or even a month. So to answer your question. Our typical full turnkey kitchen remodel can sit anywhere from 10-14 weeks, depending on the scope of work, and we are here to tell you why.
An Honest Timeline
Prior to demo day, we provide our clients with a Gantt chart. With this chart, they have a pretty good idea of what their project timeline actually looks like. Although these have some fluidity to them, it shows what all needs to be done and is shown in the general order of when these items need to be done. The most important date to consider is when the cabinets are ordered and when they will be delivered. You can see the third line in a sample project plan below that cabinets were ordered April 15 and estimated to be delivered May 30. This is about a 6 week lead time which most semi-custom cabinet lines will sit in this general range. However, if you are going fully custom, think 8-10 week lead time on average.
Phase 1
Once we have an idea of when cabinets are going to arrive, we can then move backward to cover all the steps that need to be accomplished prior to cabinets being installed, almost like a ripple effect. To start, we have prep work, demolition, framing, electrical/mechanical/ plumbing rough-ins, trenching (if needed), and rough inspections. This is what we consider as Phase 1 of any project. Phase 1 can take anywhere from 4-6 weeks, depending on the scope and how much construction really needs to be done. Engineered beam? Add a couple of days. Lots of re-framing work? Add a couple more. Measure twice, cut once – that way it’s done right and we pass inspections the first time! Check out our guys in action after demo as they lay out the trenching work that needs to be done for this future kitchen island below:
Finish Material Installation
Once we pass our rough inspections – which can take up to several days (as inspectors don’t all show up at once) we then can close everything in and start with the “visual” items. This is usually the first big change you will see since the demo day. Cabinets go in and hardware gets installed. This part of the process can take somewhere between 1 and 2 weeks to complete. Once those are in we can set up any templates we need to do: countertop, glass inserts, etc. which line out the rest of the project.
“Down Time” – Countertop Install
Countertop installation is usually one of the only “down times” we have during the project. Counters are templated after cabinets; we don’t pre-order based off of our designs. This ensures that the counters fit perfectly snug on your new cabinets. Unfortunately, counters aren’t fabricated in a day! They are templated, then put into the fabrication queue, which can take anywhere from 5-10 business days depending on the material and how busy our fabricators are. Luckily, with us, we have already ordered and paid for the material so we can usually get it done in a calendar week! If you want to actually lay out your material, as seen below, we can go to the fabricator and have this done. It’s an extra couple of days, but worth it!
The Finish Line
Once counters go in, we’ve only got a few more things on our list to finish up! Tile goes in (set, grout, and seal), appliances get installed, and we can do our electrical and plumbing finish-outs. These final items typically range from 2-4 weeks to complete, mostly depending on what we can get done at the same time. You don’t want guys tripping over each other in the field! Then finally, we can start pulling together a punch list. Maybe a cabinet door got dinged or damaged during installation – we’ll have that ordered so that we can install that as soon as we get it. Then, we finish up any additional trim painting, and we’re almost ready to wrap up the remodel!
Last, Floor Finishing
Typically, the very last step in a remodel is the floor finishing. If you have tile or engineered floors, no need for this last step as they probably have already been installed. But if you have hardwoods, now is the time. With all the other materials installed, we can stain some samples to find the perfect one to match the space. We then close down the space for almost a week to everyone (including you) so that we can sand, stain, and finish. But then, we are on to the real finish line!
That’s A Wrap!
Once the punch list is all wrapped up – a couple of days – we call in final inspections and you’re done! All you have to do now is get a deep clean. We highly recommend having a true cleaning service do this. Once everything is clean, it’s time to move in and really begin using the new space. Imagine all the time you’ve spent dreaming and planning this kitchen with us, the day is finally here! Check out this kitchen project before and after to get an idea of what your new space could look like!
See all the details on the project featured in this blog, here!
Recent Posts
Archives
- November 2023
- October 2023
- September 2023
- August 2023
- March 2023
- January 2023
- December 2022
- November 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- September 2021
- July 2021
- December 2020
- November 2020
- August 2020
- July 2020
- June 2020
- May 2020
- April 2020
- March 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- September 2019
- August 2019
- July 2019
- June 2019
- May 2019
- April 2019
- March 2019
- February 2019
- January 2019
- December 2018
- November 2018
- October 2018
- September 2018
- August 2018
- July 2018
- June 2018
- May 2018
- April 2018
- March 2018
- February 2018
- January 2018
- December 2017
- November 2017
- October 2017
- September 2017
- August 2017
- July 2017
- June 2017
- May 2017
- April 2017
- March 2017
- February 2017
- January 2017
- December 2016
- November 2016
- October 2016
- September 2016
- August 2016
- July 2016
- June 2016
- May 2016
- April 2016
- March 2016
- February 2015
- January 2015
- November 2014
- June 2014
- May 2014
- April 2014
- January 2014
- December 2013
- November 2013
- August 2013
- July 2013
- June 2013
- May 2013
- April 2013
- March 2013
- February 2013
- January 2013
- November 2012
- October 2012
- September 2012
- August 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
- January 2012
- December 2011
- November 2011
- October 2011
- September 2011
- August 2011
- July 2011
- June 2011
- May 2011
- April 2011
- March 2011
- February 2011
- January 2011
- December 2010
- November 2010
- October 2010
- September 2010
- August 2010
- July 2010
- June 2010
- May 2010
- April 2010
Recent Comments